Hi everyone,

I want to process the same path with two different power levels in the same job.
I’m engraving a glass and I need it to:

  • Perform the first pass at full power
  • Perform the second cleanup pass at a lower power

Currently, I run the first pass, then manually adjust the power and start the second pass. I need the second pass to be executed automatically without having to start it manually again.

I tried duplicating my design, but I can’t align both designs perfectly.
Is there a way, or will there be a new feature in the future, to associate two jobs with the same design?

 

Thanks,
Luca